The city permit office continues to drive us crazy. The permit office inspector came out on March 7 to inspect our temporary electrical pole. They approved it at that point (see green sticker in photo).
At that point builders called CenterPoint to have them disconnect service/meter from original house connection and move to the new pole. As of yesterday afternoon (March 16) the city had not released CenterPoint to make the change despite it being approved. Unfortunately the builder can’t really start removing the back of the house until this happens.